1. Preparation of the special plan for scaffolding formwork www.3plyplywood.com
1. A special construction plan needs to be prepared for the construction of the formwork of the construction project, and the steel pipe scaffolding support system must have a detailed calculation book. https://www.3plyplywood.com
2. The special construction plan shall be reviewed and approved in accordance with the procedures.
3. For the special construction plan of tall formwork construction, experts must be organized to demonstrate the plan.
Powered by Shandong Unique International Trade Co.,Ltd
2. Scaffolding Foundation Shandong Unique International Trade Co.,Ltd
1. The foundation should be solid and flat, the bearing capacity should meet the design requirements, and should be able to bear all the loads on the upper part of the bracket Shandong Unique International Trade Co.,Ltd
2. The bottom of the scaffold should be set with a pad according to the specifications, and the specifications of the pad should meet the requirements of the specifications https://www.3plyplywood.com
3. The vertical and horizontal sweeping poles at the bottom of the scaffolding should meet the requirements of the specification www.3plyplywood.com
4. Drainage measures should be taken for the foundation, and the drainage should be smooth Shandong Unique International Trade Co.,Ltd
5. When scaffolding is erected on the floor structure, the strength of the floor structure should be checked, and reinforcement measures should be taken if necessary. Shandong Unique International Trade Co.,Ltd
3. Steel pipe scaffolding structure requirements
1. The distance between the poles should meet the design and specification requirements Powered by Shandong Unique International Trade Co.,Ltd
2. The step distance of the horizontal rod should meet the design and specification requirements
Copyright © Shandong Unique International Trade Co.,Ltd All Rights Reserved.
3. The horizontal rod should be set continuously according to the specification requirements
4. The setting of vertical and horizontal scissor braces (fastener-type steel pipe brackets) or special inclined rods and horizontal inclined rods (gate-type steel pipe scaffolding, socket-type disk buckle steel pipe brackets) should meet the requirements of the specification Unique
4. Specification requirements for the stability of steel pipe scaffolding www.3plyplywood.com
1. When the height-to-width ratio of the scaffold is greater than the specified value, the connecting wall parts or the strengthening measures to increase the width of the frame body should be set up according to the regulations;
https://www.3plyplywood.com
2. The length of the vertical pole extending from the center line of the top horizontal pole to the support point should meet the requirements of the specification;
Shandong Unique International Trade Co.,Ltd
3. When pouring concrete, the foundation settlement of the frame body and the deformation of the frame body should be monitored, and the settlement of the foundation body and the deformation of the frame body should be within the specified allowable range. Powered by Shandong Unique International Trade Co.,Ltd
5. Construction disclosure and acceptance of steel pipe scaffolding formwork Shandong Unique International Trade Co.,Ltd
1. Before the erection and dismantling of steel pipe scaffolding, the disclosure shall be made, and there shall be a disclosure record;
www.3plyplywood.com
2. After the construction of the steel pipe scaffolding formwork is completed, the acceptance should be organized according to the regulations. The acceptance should have quantitative content and be confirmed by the person in charge.
6. Steel pipe scaffolding formwork construction, the connection of scaffolding rods should meet the requirements of the specification
https://www.3plyplywood.com
1. The pole connection should meet the specification requirements;
Unique
2. The connection of the horizontal rod should meet the specification requirements; www.3plyplywood.com
3. The length of the scissor brace diagonal rod should meet the requirements of the specification; www.3plyplywood.com
4. The fastening of each connection point of the rod should meet the requirements of the specification.
7. Scaffolding base and support
Copyright © Shandong Unique International Trade Co.,Ltd All Rights Reserved.
1. The diameter of the adjustable bottom bracket of the steel pipe and the screw of the top bracket should match the inner diameter of the vertical rod, and the matching clearance should meet the requirements of the specification. The scaffold should not be equipped with a top bracket and a bottom bracket at the same time.
www.3plyplywood.com
2. The length of the screw screw into the nut should not be less than 5 times the screw diameter. Copyright © Shandong Unique International Trade Co.,Ltd All Rights Reserved.
Eight, steel pipe scaffolding formwork construction components and accessories
1. The specifications, models and materials of steel pipes and components should meet the requirements of the specifications. www.3plyplywood.com
2. The rods shall not be bent, deformed or severely corroded. www.3plyplywood.com
3. Materials such as formwork, wood, fasteners, etc. must meet the requirements of calculation books and specifications. https://www.3plyplywood.com
Nine, steel scaffolding formwork removal
Shandong Unique International Trade Co.,Ltd
1. The concrete strength of the structure before the support is removed should meet the design requirements; www.3plyplywood.com
2. Before the dismantling of the support, it is necessary to submit an application for dismantling the formwork, and the supervisor shall issue the "Order of Dismantling of Formwork" before the dismantling of the formwork can be carried out. Unique
3. Warnings should be set up before the brackets are removed, and special personnel should be set up to monitor them.
For details, please refer to the relevant technical specifications for scaffolding formwork construction:
https://www.3plyplywood.com
"Technical Specification for Safety of Construction Formwork" JGJ 162-2008
https://www.3plyplywood.com
"Code for Loading of Building Structures" GB50009-2012
"Code for Design of Steel Structures" GB50017-2003 www.3plyplywood.com
"Code for Design of Building Foundation" GB50007-2011 Copyright © Shandong Unique International Trade Co.,Ltd All Rights Reserved.
"Technical Specification for Safety of Wooden Scaffolding in Building Construction" JGJ 164-2008
"Safety Technical Specification for Fastener Type Steel Pipe Scaffolding in Construction" JGJ130-2011
Unique
"Code for Design of Concrete Structures" GB50010-2010 Powered by Shandong Unique International Trade Co.,Ltd
Please pay attention to the "Construction Engineering Learning Garden", and will continue to share the experience and information of construction engineering.